The AI boom has a distinctly physical constraint: a data center cannot run on forecasts of future electricity. It needs power delivered where its servers sit, at the hours they need it, with enough backup to ride through a cloudy afternoon or a grid fault.

That is the bet behind a proposal from Brook Porter, a partner at G2 Venture Partners, the firm that backed AI-infrastructure developer Crusoe. In an interview with TechCrunch published Nov. 24, Porter argues that solar paired with energy storage could be built faster and scaled more readily than relying on gas generation or waiting for grid connections. His argument is an investor thesis, not an independently validated forecast.

The appeal is manufacturing scale

Porter contrasts annual global manufacturing capacity for natural-gas generation equipment—estimated by him at roughly 60 to 70 gigawatts—with solar manufacturing capacity exceeding a terawatt. Those are not equivalent measures of electricity delivered: nameplate capacity is not the same as output, and solar’s production varies with daylight and weather. The comparison does, however, capture his central point: panels and batteries can be manufactured in modular units, while large power projects and grid connections often depend on slower, site-specific permitting, construction and supply chains.

Storage is the hinge. Solar panels make electricity when sunlight is available; batteries shift some of that output to later hours. A data center needs power around the clock, so the system must be sized for more than an average sunny day. The required storage duration, backup generation and connection to the wider grid depend on local weather, workload, reliability targets and the campus’s power demand. “Off-grid” can mean independence from grid constraints in a proposal; it does not by itself establish that an actual facility can operate without other backup or firm supply.

A real deployment, with important caveats

There is evidence this pairing can serve AI computing at a smaller scale. Crusoe and Redwood Materials say their Nevada project combines on-site solar with repurposed electric-vehicle batteries in a 12-megawatt/63-megawatt-hour microgrid, powering four modular Crusoe Spark data centers. In a March 2026 announcement, the companies said the system had 99.2% operational availability over seven months and that they planned to expand the campus from four units to 24.

Those are company-reported figures, not an independent performance audit. The announcement does not provide a detailed time series, define all exclusions behind “availability,” or establish that the project can power a hyperscale campus through extended low-sun periods. Crusoe also says its broader cloud service maintains 99.9% availability while using the grid as backup—a reminder that a renewable microgrid and a fully self-sufficient, isolated power system are different claims.

The scale gap is substantial. A 12-megawatt project demonstrates a workable configuration; it does not prove that batteries and solar can supply the much larger campuses now being proposed. Long-duration storage could help bridge longer gaps, but a technology’s promised discharge duration is not the same as a commercially deployed system operating at data-center scale. The TechCrunch article presents Porter’s view that newer storage technologies may broaden the options, but the interview does not establish a fleet of such systems serving large AI campuses.

Grid independence moves the bottleneck

Solar-plus-storage could help developers avoid some grid-connection delays and make use of energy near where it is generated. But it shifts rather than erases dependencies: projects still need land, panels, inverters, batteries, transmission or local generation, controls, maintenance and a plan for extended shortages. A stand-alone campus also has to handle the consequences when its own equipment fails.

Nor is the alternative simply “renewables versus gas.” Crusoe and Neuberger Specialty Finance announced in October a $700 million facility to finance power equipment for Crusoe AI factories, with the company describing the equipment as gas generators. That company announcement does not establish the full mix at any one campus, but it shows that the developer’s near-term power strategy includes conventional generation as well as experiments with solar and storage.

Porter’s larger point is about speed: if electricity demand for AI grows faster than grids and generation can be built, modular energy systems could become part of the infrastructure race. The evidence so far supports the narrower claim that solar and repurposed batteries can power a small, modular AI-computing deployment with the grid nearby as backup. Whether the same recipe can reliably serve much larger campuses—at competitive cost, with enough storage and without quietly relying on other power—is still an open engineering and commercial question.

Sources: TechCrunch interview with Brook Porter; Crusoe and Redwood Materials’ March 2026 project announcement; Crusoe and Neuberger Specialty Finance’s October 2026 announcement. Company performance and financing statements are attributed and have not been independently audited here.